Ohio County Accelerates Cost-Effective Bridge Replacements With Steel
As part of an ongoing county-wide bridge replacement program, Ohio’s Muskingum County Engineer’s Office (MCEO) initiated the replacement of the structurally deficient Boggs Road Bridge in Perry Township, east of Zanesville, Ohio.
The original 33-foot Boggs Road Bridge, constructed in the 1950s, had begun to show signs of deterioration and MCEO had already imposed weight limits. As a common practice, MCEO performed a detailed engineering analysis to compare the cost of replacing the existing bridge with steel or concrete.
For the project, MCEO compared the cost of five galvanized steel beams with the cost of six concrete box beams which were needed to replace the short span bridge superstructure. The galvanized steel beams saved the county more than $10,000.
Since local crews did not need a crane to set 1.5-ton steel beams, which would be necessary for 17-ton box beams, MCEO realized significant additional savings on materials and equipment rental.
Added to the lower cost of materials and equipment, MCEO also secured a 35-year warranty on the galvanized coating system and the ability to rehabilitate the steel in the future.
With an eye on completing the bridge replacement as quickly as possible, MCEO initiated the detailed bridge design.
Fast-Track Design
For the Boggs Road Bridge replacement, the in-house engineering team designed a 24-foot wide steel beam structure constructed of five beam lines, five-feet on center covered with a nine-inch-thick cast-in-place composite concrete reinforced deck with no skew, placed on new concrete abutments with spread footings.
The team saved significant time and costs by planning and designing the structure in-house.
Local Crew Edge
With the design in hand, MCEO let bids for the bridge elements. The Boggs Road Bridge superstructure was fabricated by U.S. Bridge in Cambridge, Ohio with five W24x76 ASTM A709 GR 50 beams and laterally supported with C12x25 braces. The superstructure was hot-dip galvanized prior to delivery.
On May 20, 2014, MCEO crews began the removal and replacement of the bridge. The superstructure was erected on reinforced concrete abutments on spread footings. Steel 1.5C decking (manufactured by Nucor) was installed as stay-in-place forming for the main deck area and then shear studs were installed through the decking.
Then, crews used a county-designed forming system made up of W8x18 steel beams supported by the exterior beam to support the thickened 18-inch-thick deck edge, work walkway and work bridge.
Guardrail inserts were installed in the thickened deck edge prior to the installation of two mats of epoxy-coated Grade 60 reinforcing steel. Crews then poured a 4,500 psi crowned concrete deck with IPANEX® waterproofing admixture.
The Boggs Road Bridge reopened on June 20, 2014.
Long-Term Steel Focus
Muskingum County has relied on steel for many years. Today, approximately 60% of the county’s 415 bridges are steel. There are 42 steel truss bridges (one built in 1913), three steel girders, 186 steel beam bridges and 19 steel culverts.
MCEO has found that steel is strong and economical for our typical span lengths. Steel is easy to fabricate and construct, and its strength-to-weight ratio allows the county to erect most of the structures without the use of a crane.
Steel is also easy to maintain and repair, which promotes the longevity of the county’s structures.
And finally, steel is recyclable and reusable. MCEO has reused/repurposed several structures in other locations, saving tens of thousands of dollars. The cost savings of steel versus other materials―coupled with the other advantages of sustainability and easy maintenance means that the county can repair and replace more bridge structures and shorten road closures.
Quality and sustainability were also factored into the choice of steel for the Boggs Road Bridge. Steel beams are fabricated in a highly controlled process as compared to concrete that is poured by outside in varying weather conditions. MCEO also likes the fact that it can maintain and reuse steel bridge beams.
Does steel provide an economical solution for bridge construction?
- Due to the light weight of steel, cost savings can be significant
- Studies show that weathering, A1010 (A709-50CR), and galvanized steel reduces both initial and life cycle costs.
- Steel can compete and even save costs when compared with nearly identical concrete structures. re.
- Steel bridges also have long lives, decreasing the need for replacement.
- Steel’s high strength permits longer spans, minimizing disruption to underlying habitats.
- Steel is highly resistant to extreme natural disasters such as earthquakes.
- Steel is the world’s most recycled material and is infinitely recyclable.
- Short span steel bridges can be designed with prefabricated elements which provide a simpler installation and cost savings.
NSBA Posts Updated Guide to Navigating Routine Steel Bridge Design
This updated free guide from NSBA walks engineers through the design process, focusing on the specific provisions of the AASHTO specifications that apply to routine bridges.
On-Demand Steel Bridge Video Series: Learning By Example
A distinguished panel of 8 industry experts to present case studies that offer innovative and cost-effective examples of steel bridge replacement projects.
Steel Industry Accelerates Rebuild of I-95 Bridge Project
Cleveland Cliffs is providing steel to High Steel Structures for the accelerated permanent reconstruction of a bridge section of I-95 in Philadelphia that collapsed in June.