Buried Bridge NCSPA Award Winner

Johnson Creek Buried Bridge Wins NCSPA Project of the Year Award

Article provided by Contech Engineered Solutions and the National Corrugated Steel Pipe Association

The Johnson Creek project involved removing a fish barrier and replacing it with a fish-friendly, bottomless arch. These types of projects are generically called AOP’s (aquatic organism passages ) or simply fish passage projects. Fish passages allow for various species of fish to travel as far up a stream as they historically did to spawn prior to a barrier being placed in the stream.

The challenges on this project involved a deep excavation to get down to the streambed elevation, construct a bypass road with very steep side embankments, assemble a plate structure in the excavation, and complete by the end of the fish passage window ( spawning season ), or when the fish would begin their trek upstream.

The steel buried bridge was completed in less than 8 days for the 83′ long structure.

The project was partially funded by the North Olympic Salmon Coalition, a non-profit salmon enhancement group. The plate was ordered the last week of May 2020 and arrived on site the first week of August 2020.

Prior to the plate arriving, Interwest Construction had completed the deep excavation, established a stream bypass and constructed the temporary bypass road. Hoko-Ozette Road is in a remote area and establishing a detour route was impossible, so the temporary bypass road was required. They had also completed the installation of the reinforced concrete footings for the arch foundation.

Assembly was completed in less than 8 days for the 83′ long structure. Staging the required equipment in a such a deep excavation was difficult but went as planned. The structure was then backfilled with the prescribed backfill materials and compacted to the required compaction level.

The project was completed on-time and the salmon have successfully moved upstream in the first spawning season after the construction.

Mechanically stabilized earth (MSE) headwalls were constructed at each end as the backfilling proceeded. Above the wirewall headwalls, Interwest Construction then built steep embankment slopes with planted local vegetation to complement the surrounding area.

The project was completed within the allotted time frame and the salmon have successfully already moved upstream in the first spawning season after the construction.

View Original Article

Related Resources: Buried Bridges

National Corrugated Steel Pipe Association Logo

NCSPA Announces 2024 Project of the Year Winners

The National Corrugated Steel Pipe Association announced the 2024 project of the year winners, including three members of the Short Span Steel Bridge Alliance.

Railroad Corrugated Pipe Project

Corrugated Steel Pipe Safeguards Rail System from Excessive Storm Water

The National Corrugated Steel Pipe Association (NCSPA) spotlights a project that used corrugated steel pipe to provide a storm water solution in only 8 hours.

New Resiliency Video Compares Corrugated Steel Pipe to Other Materials

The National Corrugated Steel Pipe Association (NCSPA) launched a new video focused on the resiliency of corrugated steel pipe – commonly used in buried steel bridges.

Rail Bridge

Funding On Its Way for Rail Bridges

The Biden administration announced $16.4 billion for rail projects along Amtrak’s Northeast Corridor as part of the overall investments in infrastructure.

Steel Bridge Webinar Series

On-Demand Steel Bridge Video Series: Learning By Example

A distinguished panel of 8 industry experts to present case studies that offer innovative and cost-effective examples of steel bridge replacement projects.

Buried Steel Bridge

October 31: Webinar – Demonstrated Performance of Buried Bridges

The American Galvanizers Association invites you to attend a 1-hour webinar sustainable development and hot-dip galvanizing.