Boggs Road Bridge

Muskingum County’s Short Span Steel Bridge Solution – Quicker, More Cost-Effective and Constructed in 30 Days!

When the Muskingum County (Ohio) Engineers Office (MCEO) needed to replace the structurally deficient Boggs Road Bridge near Zanesville, a detailed engineering analysis was conducted to compare the cost of replacing the existing bridge with steel or concrete.

The original 33-foot bridge built in the 1950s was showing signs of deterioration, and weight limits had been imposed. Muskingum County Engineer Douglas R. Davis, P.E., P.S., compared the cost of five galvanized steel beams with the cost of six concrete box beams which were needed to replace the bridge superstructure. His engineering analysis found that:

  • He could save $10,000 by choosing the five galvanized steel beams for the superstructure.
  • He could use his local crew to do the work since they would not need a crane to set the 1.5-ton steel beams, saving significant costs on materials and equipment rental.
  • He was able to secure a 35-year warranty on the galvanized coating system and the ability to rehabilitate the steel in the future.
Boggs Road Steel Bridge

The bridge was constructed of five beam lines, five-feet on center covered with a nine-inch-thick cast-in-place composite concrete reinforced deck.

Additional costs were attained by designing the 24-foot wide steel beam structure in-house. The new Boggs Road Bridge was constructed of five beam lines, five-feet on center covered with a nine-inch-thick cast-in-place composite concrete reinforced deck with no skew, placed on new concrete abutments with spread footings.

The superstructure was fabricated by U.S. Bridge in Cambridge, Ohio and hot-dip galvanized prior to delivery. MCEO crews began the removal and replacement of the bridge on May 20, 2014, and the new bridge reopened to traffic just one month later.

MCEO likes steel, and approximately 60 percent of the county’s 415 bridges are steel. The inventory includes 42 steel truss bridges (one built in 1913), three steel girders, 186 steel beam bridges and 19 steel culverts (buried soil steel structures).

Why choose steel? Because steel is:

  • Strong and economical for the county’s typical span lengths.
  • Easy to fabricate and construct.
  • Easy to install, with a strength-to-weight ratio that allows most structures to be erected without the use of a crane.
  • Easy to maintain and repair, which promotes structure longevity.
  • Recyclable and reusable, allowing steel structures to be reused or repurposed in other locations, saving tens of thousands of dollars.

A new web-based design tool, eSPAN140, allows users to receive preliminary customized short span steel bridge designs in three easy steps and at no cost, with results in less than five minutes.

Do you have a creative short span steel bridge solution? Click here to tell us about it.

Related Resources: Rolled Beam & Plate Girder Bridges

Bridges of Franklin County: Why Missouri is Turning to Steel weathering steel short span bridge

Bridges of Franklin County: Why Missouri is Turning to Steel

Franklin County, Missouri, saved $283,000 by selecting steel over concrete for four short-span bridge projects, demonstrating that simplified designs combined with a competitive bidding process can deliver exceptional value, durability and long-term performance.

Modern Steel PA Bridge High Steel

“New and Improved” – Modern Steel Construction

In an article from Modern Steel Construction, the emergency replacement of a damaged northwest Pennsylvania bridge resulted in a safer, more efficient steel bridge, with SSSBA member High Steel Structures as the fabricator and detailer for the project.

Steel in Action Webinar Series

Steel in Action: On-Demand Steel Bridge Video Series

Watch this four-part, on-demand video series featuring expert-led case studies on cost-effective, resilient short span bridge projects—now available with downloadable presentation materials.

Assonet River Railroad Bridge in Assonet, Massachusetts, Steel Modular

Galvanized Steel Railway Bridge Assembled Off-Site, Installed in 11-Days

The Assonet River Railroad Bridge in Massachusetts was fully assembled off-site using galvanized steel and installed in just 11 days, minimizing environmental impact and ensuring long-term durability for expanded commuter rail service.

galvanized short span steel bridge mercer county pennsylvania

Pennsylvania County Selects Hot-Dip Galvanized Steel for Urgent Bridge Project

For a recent bridge replacement, Mercer County chose a hot-dip galvanized steel bridge to ensure a durable, cost-effective solution that could be delivered quickly and withstand a corrosive environment.

Whitman County Steel Bridge

Whitman County Saves 32 Percent with Steel Superstructure

By choosing a steel beam girder bridge, the county reduced the overall project costs and decreased the time for construction.