WV DOT Completes Fast-Track Bridge Project with Steel

WV DOT Completes Fast-Track Bridge Project with Steel

June 11, 2026

Image Credit: West Virginia Department of Transportation

A bridge near the Kanawha State Forest campground in Kanawha County, West Virginia was recently reopened following an accelerated replacement project that utilized salvaged steel beams from a nearby transportation project, demonstrating the practical benefits of steel reuse in bridge construction.

Project Overview

A 20-foot span serving access to the Kanawha State Forest campground was reopened following a short-term closure that began May 15, according to WCHS-TV (wchstv.com) and the West Virginia Department of Transportation (WV DOT). The bridge was returned to service after crews completed a rapid replacement effort.

Steel Reuse Strategy

A key feature of the project was the reuse of structural steel salvaged from the Montrose Drive Overpass Bridge project in South Charleston. Rather than fabricating and delivering new beams, WV DOT repurposed existing steel elements that were available from a completed project.

The construction approach included:

  • Removal of the existing bridge deck
  • Installation of salvaged steel support beams from the Montrose Drive Overpass project
  • Placement of reinforcing steel
  • Construction of a new concrete bridge deck

WV DOT noted that the salvaged beams were in good condition and suitable for reuse in the replacement structure.

Project Outcomes

According to WV DOT, the use of recycled materials helped reduce costs and expedited the construction schedule, allowing the bridge to reopen shortly after work began. The project restored access to the Kanawha State Forest campground area following the brief closure period.

Implications for Steel Bridge Construction

This project illustrates how steel bridge components can be effectively reused as an alternative to improve resource efficiency in transportation projects. The ability to repurpose steel from one project to another highlights a practical advantage of steel in bridge applications, particularly for agencies seeking efficient use of existing materials.

View additional images for the project from the West Virginia Department of Transportation:

Related Resources: News

Steel Bridge Design Tools Featured at IBC Session Support Streamlined Bridge Delivery

Steel Bridge Design Tools Featured at IBC Sessions Support Streamlined Bridge Delivery

SSSBA supported sessions at the 2026 International Bridge Conference highlighted integrated steel bridge design tools that support efficient project delivery. Presenters showcased resources including eSPAN140, eBEAM140, LRFD Simon and AISC NSBA Standard Bridge Plans, drawing strong interest from bridge owners and designers.

U.S. Transportation Secretary Sean P. Duffy announced a $626.7 million investment in America's infrastructure. Eligible projects include repairing highways and bridges to reduce traffic congestion and freight bottlenecks.

USDOT Makes $626M Available for Infrastructure Projects

U.S. Transportation Secretary Sean P. Duffy announced a $626.7 million investment in America’s infrastructure. Eligible projects include repairing highways and bridges to reduce traffic congestion and freight bottlenecks.

SSSBA to Sponsor Two Educational Sessions at the 2026 International Bridge Conference (July 15-17)

SSSBA to Sponsor Two Educational Sessions at the 2026 International Bridge Conference (June 15-17)

The SSSBA will participate in two educational sessions at the 2026 International Bridge Conference, taking place at the National Harbor, Maryland. Attendees will learn how tools such as eBEAM140, eSPAN140, LRFD Simon and AISC/NSBA Standard Plans can help streamline steel bridge design, improve decision-making and enhance project efficiency.